S-34.1, r. 1 - Regulation respecting petroleum exploration, production and storage in a body of water

Full text
66. The authorization holder must comply with the technical program.
The holder may modify the program by sending to the Minister a supplementary agreement signed and sealed by an engineer stating the nature of the modification and the reasons justifying it. The supplementary agreement must be sent to the Minister before carrying out the work covered by the agreement. If it is urgent to modify the technical program for safety or work quality purposes, the holder must immediately send the agreement to the Minister and justify the urgency.
A supplementary agreement to the technical program is not required in the following cases:
(1)  an adjustment of less than 10% in the final depth of the stratigraphic survey resulting in a slightly different geological projection;
(2)  a change in the position of the casing head of the stratigraphic survey where it remains on the activity site;
(3)  the addition or cancellation of a coring section, a drill-stem test, a well log, a sample collection or a fluid sample.
In the situations provided for in the third paragraph, the holder immediately informs the Minister of the change to the technical program.
O.C. 1251-2018, s. 66.
In force: 2018-09-20
66. The authorization holder must comply with the technical program.
The holder may modify the program by sending to the Minister a supplementary agreement signed and sealed by an engineer stating the nature of the modification and the reasons justifying it. The supplementary agreement must be sent to the Minister before carrying out the work covered by the agreement. If it is urgent to modify the technical program for safety or work quality purposes, the holder must immediately send the agreement to the Minister and justify the urgency.
A supplementary agreement to the technical program is not required in the following cases:
(1)  an adjustment of less than 10% in the final depth of the stratigraphic survey resulting in a slightly different geological projection;
(2)  a change in the position of the casing head of the stratigraphic survey where it remains on the activity site;
(3)  the addition or cancellation of a coring section, a drill-stem test, a well log, a sample collection or a fluid sample.
In the situations provided for in the third paragraph, the holder immediately informs the Minister of the change to the technical program.
O.C. 1251-2018, s. 66.